Addendum to the Risk Assessment Matrix

Description of Risks

Impact Likelihood of Occurrence (L,M,H) Degree of Impact (L,M,H) Initial Action to Take if Event Occurs Team Member Responsible Strategies for Prevention and Mitigation Widespread safety breach because of unauthorized access to delicate buyer information. Negative publicity of the company and lack of credibility in the eyes of present and potential prospects impacting general business. Take instant motion to tighten security including all worker access to customer sensitive information.

Don’t waste time Get a verified expert to help you with Essay


Identify and set up the latest safety software program on all telecommuters’ PCs and enforce strict guidelines for info entry including password policy management.

Document Server integration challenges. The setup of the setting for the Telecommuters could be delayed. roubleshoot remotely to identify the basis of the integration problem. The repetitive means of installation and setup of the document servers could be probably scripted and semi-automated to reduce error and scale back time taken. Technical challenges such as energy failure and web connection outages. The setup of the environment for the Telecommuters can be delayed if both energy or web connection were impacted.

Guidelines can cover directions to move on to the subsequent pc to setup and return to the remote PC with power or internet challenges later.PhoebeTo prevent and mitigate this threat, the telecommuter PCs can be staged and setup within the Xemba Translations office earlier than shipping to the remote location.

In the lengthy run finances can be allocated for individual battery backup for the distant PCs Delay in completion of the Telecommuting Expansion projectInadequate assets out there to handle the elevated customer need causing adverse publicity of the corporate.

Increase the project group measurement to catch up and pace up progress decreasing potential for any additional schedule impression.Project TeamManage schedules much more tightly monitoring day by day progress of duties and mitigating schedule delays even earlier than it occurs. Perception of impersonal and below par service due to telecommuters Though there’s a subjective facet to this danger it can result in the lack of very actual customers and negative publicity. Focus can be shifted to the lost prospects to survey the explanation for them to take enterprise elsewhere and offer incentives to return. Work with the advertising group to make sure the message is obvious to giant clients on the advantages of real-time web primarily based communications and translation services.

Task B: Explanation of Metrics: The metrics that might be effectively used to clearly and effectively measure the progress and total project well being of this Telecommuter Expansion project is “Earned Value Management”. It is a generally used technique that elements in the price and schedule baselines and then makes use of simple indices to estimate and measure the place the project is in reference to the respective projected baselines that had been set firstly of the project. Earned Value Management relies on three key metrics: – Planned Value (PV): This is the official price range that has been allotted to the project. The price range is usually setup per phase of the project, but at any point in time the “Planned Value” is used to refer to the work that ought to have been completed. The complete deliberate worth for the project is also referred to as the “Budget at Completion” (BAC) – Earned Value (EV): The Earned Value refers again to the amount of work that would need to be completed at any point in time in for the project to be thought of to be on observe. The Earned Value is usually used to calculate the percent complete for any project. The formula for p.c complete can be: % Complete = EV / BAC. – Actual Cost (AC): The Actual Cost would fairly merely be the costs which have been incurred to accomplish all the work performed thus far in a project. Technically the AC will have no higher restrict and translates all the time to what was budgeted in the PV and measured by the EV. Part of the Earned Value Management method is the monitoring of variances from the permitted baseline of prices and schedule.

The variances are useful in determining the general project well being and status. – Schedule Variance (SV): The Schedule Variance signifies a price which is a measure of how much the project is either ahead or behind at a given cut-off date. For any given time limit, once the EV and PV are recognized the SV can simply be calculated. The formula for SV is sort of merely: SV = EV – PV. Here a optimistic worth signifies that the project is forward at the present time limit and a adverse worth would point out the alternative that a project is behind on the present time limit. – Cost Variance (CV): The Cost Variance signifies a worth which is a measure of how a lot the project is either overspent or underspent at any given point in time. For any given cut-off date, as quickly as the EV and AC are recognized the CV can easily be calculated. The formula for CV is type of simply: CV = EV – AC. Here a positive value indicates that the project is beneath spent at the present time limit and a adverse value would indicate the alternative that a project is over spent on the present time limit.

The Cost Variance on the end of the project is calculated as follows: CV = BAC – AC. The similar above rationale is applied to constructive and unfavorable numbers to indicate if the project is beneath spent or over spent respectively. To measure schedule or value efficiency there are two indices which are additionally computed as part of the Earned Value Management approach. They are Schedule Performance Index and Cost Performance Index. – Schedule Performance Index (SPI): This is a measure of how effectively the project has been run till the present time limit. An SPI of less than 1.zero would indicate that much less work was completed than originally deliberate and an SPI value greater than 1.0 would point out that extra work was accomplished than was originally deliberate. The SPI is calculated with the following formulation: SPI = EV / PV – Cost Performance Index (CPI): This is a measure of how effectively the project has been run when it comes to budgeted assets until the current cut-off date. The CPI is taken into account essentially the most important metric of the Earned Value Management methodology. A CPI of lower than 1.0 would indicate that the project is at present over finances than initially planned and a CPI worth of greater than 1.zero would point out that the project is presently under price range and in good shape. The CPI is calculated with the following formula: CPI = EV / AC

Task B1: Justification of Metrics: One of the first reasons of selecting the Earned Value Management methodology for the tracking of the project metrics of the Telecommuting Expansion Project was as a outcome of the fact that this methodology comprehensively covers all the key elements of Project Schedule Control and Cost Management. With using this method a well-rounded analysis could be performed on the data offered. The data supplied has the clear worth for the finances at completion (BAC) for all the labor costs for the project as nicely. The Cash Flow Report offered in the case research offers an excellent reference of the Earned Value at the 76 day mark within week 11. The Status Reports that are provided on the end of the Case Study also offers the detailed precise sunk costs for each work bundle coated within the project work breakdown construction.

Using the details offered, the Cost and Schedule Variances can easily be calculated which would simply offer a detailed take a glance at the general project well being with reference to schedule and cost. With a easy arithmetic calculation one can easily determine whether the project is on track to stay beneath budget or go over finances in addition to decide whether the project goes to remain on monitor and full on schedule, or early or late. Also, with the calculation of the Cost Performance Index and the Schedule Performance Index, the schedule effectivity and cost effectivity of the Project could be easily evaluated. Comparing the two indices in reference to them being greater than 1.0 or lesser than 1.0 one can predict if the project is on track to return in under or over budget and end ahead or not on time. This approach additionally matches properly with the important path approach that has been used so far within the case research the place special emphasis can be paid to the work packages in the critical path in an effort to additional mitigate threat and control schedule and costs of the project.

Task B2: Current Project Status: The following desk is an entire summary of the fifteen project group members and their associated labor costs that have been planned initially of the project as nicely as the revised plan per the project manager’s

Status report: Resource NameRate per HourPlanned HoursBudgeted Labor CostWBS ItemHours WorkedHours LeftRevised Work PlanSpent CostsFuture Costs% Left Elizabeth $ 70.00 121.43 $ eight,500.10 11220122 $ 8,540.00 $ – 0% Hugh $ 70.00 120 $ eight,four hundred.00 210317120 $ 7,210.00 $ 1,190.00 14% Kimberly $ 70.00 seventy six $ 5,320.00 3721688 $ 5,040.00 $ 1,one hundred twenty.00 21% Phoebe $ 68.00 98 $ 6,664.00 4762096 $ 5,168.00 $ 1,360.00 20% Ben $ 68.00 138 $ 9,384.00 59352145 $ 6,324.00 $ 3,536.00 38% Zeke $ sixty five.00 384.sixty seven $ 25,003.55 6153245398 $ 9,945.00 $ 15,925.00 64% Malinda $ 75.00 224 $ sixteen,800.00 758160218 $ four,350.00 $ 12,000.00 71% Willis $ 70.00 108 $ 7,560.00 816068228 $ 11,200.00 $ 4,760.00 63% Jackson $ forty five.00 268 $ 12,060.00 2,four,5177112289 $ 7,965.00 $ 5,040.00 42% Kendrick $ forty.00 seventy eight $ 3,120.00 586086 $
three,440.00 $ – 0% Marcel $ 75.00 432.85 $ 32,463.75 1,four,5,7268200468 $ 20,100.00 $ 15,000.00 46% Lianne $ 37.50 204 $ 7,650.00 3,8170110280 $ 6,375.00 $ four,a hundred twenty five.00 54% Darius $ 55.00 72 $ 3,960.00 three,8304272 $ 1,650.00 $ 2,310.00 58% Valene $ 60.00 one hundred fifty $ 9,000.00 4,5,611664180 $ 6,960.00 $ three,840.00 43% Clemencia $ 80.00 218.05 $ 17,444.00 1,6104114218 $ eight,320.00 $ 9,120.00 52% 2693 $ 173,329.forty 178812203008 $ 112,587.00 $ 79,326.00 41%

Notes: Looking on the above abstract, the following can be summarized:

Planned Labor Cost (PV/BAC): $ 173,329.40
Labor Costs spent (AC):$ 112,587.00
Remaining Labor Costs:$ 79,326.00
Initial Labor Plan:2693 hours
Revised Labor Plan:3008 hours
Hours Spent:1788 hours
Hours Remaining:1220 hours
Based on the Initial Labor Plan the following are computed: o% Complete: Hours spent / Initial Labor Plan
1788 / 2693 = 66%

Based on the Revised Labor Plan the next are computed: o% Complete:Hours spent / Revised Labor Plan
1788 / 3008 = 59%
o% Remaining:Hours remaining / Revised Labor Plan
1220/ 2008 = 41%
Since the PV, AC and % Complete are identified, the following metrics which are part of the Earned Value Management Plan are computed: •Earned Value (EV) = BAC x % Complete
= $ 173, 329.forty x 59%
= $ 102, 264.35
Cost Variance (CV) = EV – AC = $102,264.35 – $112,587.00 = -$10,322.65
Schedule Variance (SV) = EV – PV = $102,264.35 – $173,329.forty = -$71,065.05 Note: Since both the Cost and Schedule Variances are unfavorable, this means that the project is presently trending “over budget” and presently running not on time.

Cost Performance Index (CPI)= EV / AC

= $102,264.35 / $112,587.00
= .91
Schedule Performance Index (SPI)= EV / PV
= $102,264.35 / $173,329.40
= .59
Note: Since both the Cost and Schedule Performance Indices are lesser than 1.zero then this may point out that the Project will finish over price range and will finish late.

Using the formulation within the Earned Value Management approach, the final project value and the final project length can be estimated. Per the Case Study, the initial planned length for the project is 123 days.

Estimated Final Project Cost = BAC / CPI

= $ 173,329.40 / .91
= $ a hundred ninety,471.87

Estimated Final Project Duration = Planned Duration / SPI
= 123 days / .59
= 209 days

Note: Unless mitigated further the labor prices for the project might be round $ 17K more than deliberate and will finish around 86 days late. The extra prices for the project are the procurement prices for the hardware and software program to assist the 173 telecommuters. These would include the prices for the new computers that the telecommuters would use in addition to the Document Servers, Shared Drives, FTP Servers, Firewalls and the assist for Web-Based conferences. Based on the details provided in the Status Report by the earlier project supervisor for the Xemba Translations Telecommuter Expansion Project, the entire budgeted amount for all of those costs was $73,670.57. Per that very same report the next desk accommodates the estimated actual prices for these items. ResponsibleTask NameWBS ItemHW Costs – Option 1HW Costs – Option 2Cost Details ElizabethComputer inventory and requirements1$11,four hundred.00 $14,200.00 Cost for 12 additional computer systems for the telecommuters. Option 1 – Desktops

Option 2 – Laptops
HughTechnical support2$0.00 $0.00
KimberlyComputing support3$0.00 $0.00
PhoebeDocument servers4$34,600.00 $89,268.00 Cost for document servers for the 173 telecommuters. Option 1 – $200 for 50GB per person
Option 2 – $516 for 100GB per person

BenShared Drives5$17,300.00 $17,300.00 Cost for shared drives for the 173 telecommuters. The value is estimated at $20 per 10GB. Each usr will use a mean of 50GB. Total value of $100 per person. ZekeFTP Sites6$6,000.00 $6,000.00 Estimated annual cost for 1000GB space for storing with limitless bandwidth for file transfers and limitless simultaneous logins MalindaFirewalls7$20,000.00 $20,000.00 Cost of firewall software program and hardware WillisWeb-Based Meetings8$2,000.00 $2,000.00 Cost between $1000 and $2000 per yr based mostly on used of web meetings $91,300.00 $148,768.00

Per the small print included in the above table, the whole prices for all of the hardware and software program to help the needs for the 173 telecommuters are more than the budgeted quantity by $17,629.forty three on the lower end and potentially more relying on configuration chosen. Per Xemba Translations CEO, Phuong Wolfing, the prices of the firewall might easily be absorbed into the overall IT budget somewhat than being accounted for as a project cost. This would imply that the hardware and software program prices for the Telecommuter Expansion Project would total to $71,300 and are available in under price range. Xemba Translations Senior Management and Stakeholders might need to decide on how to proceed here.

Task B3a: Problems Affecting Project Implementation: A abstract of three issues that might influence the project are as follows: One: Cost Overrun – Based on the current project status and development of actions together with estimates from the project team of how much more time is required on the different project tasks, if there aren’t any main modifications, the Project will definitely run well over price range and require further funding in order to
be accomplished. This would mean that there would actually have to be a fair larger effort by the new Project Manager to regulate costs to reduce the price overruns. Since the deliberate project length is 123 days, with 76 days of this project completed, this project should be approximately 62% accomplished. Till date, the Actual Cost (AC) for labor on the project is just $112,587. Looking at the Cash Flow Report which is a part of the Baseline Project Report, it reveals that on day 76, the Earned Value (EV) of the project ought to be round $125,000 with a Percent of Work Complete at approximately 72%. Calculating the Cost Performance Index (CPI) using the EV of $125,000 and AC of $112,587 would give us a worth greater than 1.zero (1.12) which might indicate that the project is currently underneath budget.

However, factoring in the new estimates of the quantity of labor remaining, the Percent of Work Remaining comes in at ~41% which would imply that the project is simply 59% accomplished when it comes to tasks. Using the “% complete” at 59% and the Planned Value (PV or BAC) of $173,329.forty we arrive at an EV of $102,587 with a unfavorable CPI lesser than 1.0 (0.91) indicating a particular cost overrun if one thing isn’t carried out and the project costs aren’t managed more tightly moving ahead. Two: Schedule Overrun – Based on the present project status and development of actions, if there are not any main changes, the Project will certainly finish properly beyond the targeted end date on the end of June in time for the start of the third quarter of the yr as anticipated when the project was permitted. This will suggest that if Senior Management and Stakeholders of this project are severe on this project being accomplished in time for the third quarter of the 12 months, then many important steps will must be taken to try and mitigate and minimize additional project delay. There had been many contributing factors leading to the delay. One of the largest contributing components for the delay within the project schedule is the time misplaced in the pilot checks of the a quantity of web-based conferences that had been deliberate and that needed to be re-scheduled because of the weather related power outage skilled in the Midwest. Another issue contributing to delay in the schedule is the procurement delay of the forty seven new computers which were delayed by two weeks due to being “back-ordered. This contributed to a late begin of the setup and validation of the forty seven new computers for the telecommuters.

As discussed within the “Project Status” part the Schedule Performance Index (SPI) is calculated to be zero.fifty nine. Since this worth is under 1.zero this indicates that the project is presently delayed and will more than likely be accomplished a lot behind schedule if the factors contributing to the delay are not mitigated. There will must be close consideration to the gadgets which are in the crucial path to see if they are often accelerated to attempt to decrease delay moving ahead. Three: Quality Challenges – The status report for the Telecommuter Expansion project that’s included as a part of the case research reveals that typically in any IT Project there are numerous components which may simply drive down the quality of the solution that is being worked on. In this case for Xemba Translations the Telecommuter Expansion is a project which includes substantial capital funding in data technology infrastructure and the associated complexities of getting the infrastructure setup and useful. As with any complex know-how solution, essentially the most crucial half includes the initial setup and verification of the complicated solution particularly in all the many edge instances where the solution’s resilience to security assaults and malicious customers is examined. Something which is not specific just to this Telecommuter Expansion project is the strain on sources that’s usually skilled in an extremely pronounced way when there are schedule associated challenges in a project.

This project is tremendously behind schedule and there are tons of essential schedule related decisions which is in a position to need to be made as part of the overall progress on this project. Another item that absolutely cannot be ignored is the Quality Management of all the shifting items of the project. For example, this project entails the setup of computers for 173 telecommuters which include establishing doc server entry for each of them, shared drives, FTP access and the required software and hardware to support a web-based assembly environment for each of the 173 telecommuters. While this seems a tall order for a gaggle of 15 project group members, it adds extra pressure when all this must be completed flawlessly when the project is already not on time. Typically when there are schedule related pressures, the tendency is to just complete an item with out focusing much on high quality. Given the technical complexity of the deliverables of this project compounded with the shortage of sufficient assets, there must be steps taken to make sure overall high quality of all of the technical deliverables in the project are maintained at a excessive degree for the successful completion of this project adopted with the successful operation of day by day actions in Xemba Translations.

Task B3b: Recommendations for Problem Mitigation: The following is a abstract of the mitigation steps to deal with the above talked about problems that could negatively impression the project. Although the problems which were encountered thus far can’t be eliminated, moving forward within the project, till completion the identical issues may be minimized or mitigated. Based on the present project status, if we the project is on day 76 out of a deliberate 123 days of project exercise and have spent $112K out of a budgeted 173K, then there’s a lot of room for tighter fiscal control and cost management. There must be processes in place to substantiate and authorize the need for additional hours spent on an activity especially if that activity is behind schedule. For instance, there has been substantial amount of time spent on the Web-Based Meetings pilot take a look at. This is an exercise where bad climate played a task in causing surprising delays in addition to pointless hours spent on an exercise which yielded no outcomes. Since we can not turn back the clock here, moving forward on any planned end-to-end testing activity, there must be a quick go/no-go name to first discuss readiness for such exercise. Also, there needs to be more diligence paid to estimation of task period.

Given that we’ve an precise observe document of how lengthy totally different task take, the activity can we more tightly estimated and the period exactly planned for. This not only helps with price estimation but also helps with scheduling control. As part of due diligence and planning, there can be a “best practices review” organized by the Project Manager where the project staff reviews greatest practices for a task that needs to be labored on and accomplished in the effort to further speed up the speed of progress whereas also not directly bringing in completion dates and shortening the schedule where attainable. Given the revised estimates of the remaining 1220 hours of work left on the project, there is a nice opportunity to herald those dates and reduce the hours spent as the identical time. Also, authorization could be obtained from Senior Management on the potential of incentivizing the team with spot bonuses if budget could be allotted accordingly, in order to maintain sure tight deadlines. This helps the group focus and work collectively to attain the frequent goal.

On one other observe on the subject of hours spent on the project by the project group, a course of may be reviewed with the staff and proposals could be made to Senior Management weekly on whether or not overtime hours for employees who shall be working their full forty hours for the week may be authorized or not. This will not solely keep a handle on prices because of overtime-pay, this may even forestall a certain element of “burnout” throughout the staff where the staff would really feel overworked. Historically, overworked groups tend to make errors and produce low quality deliverables. Hence at all costs, group burnout will must be averted which would indirectly additionally enhance general quality and staff responsiveness. Quality could be very relative and subjective. In order to take out the subjectivity from high quality measurement, the staff can be asked to work together and provide you with tangible metrics to measure the standard of all the technical deliverables that are labored on. This will serve in acquiring an unbiased and tangible view of the progress made on any of the technical deliverables and measure readiness of the solution that is being labored on. In general this same course of can be applied to the processes used for establishing the brand new computers, document servers, shared drives, FTP sites in addition to the web-based assembly software environment.

Task C: Executive Summary: The Telecommuting Expansion project is nicely underway. Another Risk Analysis was carried out and new risks have been identified and summarized in a Risk Assessment Matrix. A quick summary of the newly identified dangers, its impression and techniques for prevention and mitigation are as follows: Description of Risks Impact Strategies for Prevention and Mitigation Widespread safety breach as a outcome of unauthorized access to sensitive buyer informationNegative publicity of the corporate and loss of credibility in the eyes of existing and potential prospects impacting total businessIdentify and install the latest security software on all telecommuters’ PCs and implement strict rules for data entry together with password coverage management. Document Server integration challengesThe setup of the surroundings for the Telecommuters can be delayedThe repetitive strategy of set up and setup of the document servers could be potentially scripted and semi-automated to reduce error and cut back time taken. Technical challenges similar to power failure and web connection outages.

The setup of the surroundings for the Telecommuters could be delayed if either power or web connection were impacted. To prevent and mitigate this threat, the telecommuter PCs could be staged and setup within the Xemba Translations office earlier than shipping to the distant location. In the long run finances could be allocated for particular person battery backup for the remote PCs Delay in completion of the Telecommuting Expansion projectInadequate sources available to handle the increased customer need causing adverse publicity of the company.Manage schedules even more tightly monitoring day by day progress of tasks and mitigating schedule delays even before it happens. Perception of impersonal and below par service as a end result of telecommuters Though there is a subjective facet to this threat it might possibly lead to the loss of very actual customers and unfavorable publicityWork with the advertising staff to ensure the message is evident to massive clients on the benefits of real-time net based mostly communications and translation providers.

The project is at day 76 since its inception. There have been some changes to the initial estimates of schedule and prices to the project. The Earned Value Management technique was used to compute some key schedule and finances metrics for comparison and strategic planning of the project. The following desk has a summary of key initially planned and revised estimates of the Schedule and Budget items of the project:

Schedule/Budget ItemInitially Planned Revised Estimates

Duration in Days123 days209 days
Duration in Hours2,693 hrs3,008 hrs
Personnel Cost$173,329.40$190,471.87
Hardware/Software Cost$73,670.57$71,300.00

Note: There is further firewall hardware and software price of $20,000 which might be accounted for in the IT price range per steering from CEO – Phuong Wolfing as a substitute of being added to the Telecommuting Expansion Project costs. This value is excluded within the estimates in the above table. In addition to the above revised estimates, an evaluation was carried out on three problems that the project is going through and proposals had been summarized to address and mitigate the problems. The problems that were mentioned and summarized in nice element together with suggestions to handle the foundation of the respective issues are as follows: One: Cost Overrun – Based on the current project status and development of activities together with estimates from the project group of how much more time is needed on the totally different project duties, if there are no main adjustments, the Project will definitely run nicely over finances and require extra funding so as to be completed.

This would mean that there would really must be an even greater effort by the model new Project Manager to regulate prices to reduce the cost overruns. Two: Schedule Overrun – Based on the present project standing and trend of actions, if there are no main adjustments, the Project will certainly finish well past the focused finish date at the end of June in time for the start of the third quarter of the yr as expected when the project was permitted. This will imply that if Senior Management and Stakeholders of this project are severe on this project being accomplished in time for the third quarter of the year, then many important steps will have to be taken to attempt and mitigate and decrease further project delay. Three: Quality Challenges – The standing report for the Telecommuter Expansion project that’s included as a half of the case study reveals that usually in any IT Project there are lots of factors which may easily drive down the quality of the solution that is being labored on.

In this case for Xemba Translations the Telecommuter Expansion is a project which entails substantial capital funding in information know-how infrastructure and the related complexities of getting the infrastructure setup and functional. As with any complicated expertise answer, probably the most critical half entails the initial setup and verification of the advanced solution particularly in all the many edge circumstances where the solution’s resilience to safety assaults and malicious users is tested. Given the technical complexity of the deliverables of this project compounded with the dearth of enough sources, there must be steps taken to ensure overall quality of all the technical deliverables within the project are maintained at a high stage for the profitable completion of this project followed with the profitable operation of day by day actions in Xemba Translations. Although the problems that have been encountered up to now can’t be eradicated, transferring forward within the project, till completion the identical problems may be minimized or mitigated.

The suggestions to address the problems going through the project are as follows: Authorization for added work: There must be processes in place to substantiate and authorize the need for extra hours spent on an activity especially if that activity is not on time. Since we can’t flip back the clock here and undo any issues already experienced, transferring forward on any planned end-to-end testing exercise, there must be a quick go/no-go call to first discuss readiness for such activity. Accuracy of Task Estimation with Best Practices: Also, there must be extra diligence paid to estimation of task duration. Given that we have an precise track report of how lengthy different task take, the exercise can we extra tightly estimated and the duration exactly planned for. This not solely helps with value estimation but additionally helps with scheduling management.

As a part of due diligence and planning, there may also be a “best practices review” organized by the Project Manager the place the project staff critiques best practices for a task that must be labored on and achieved in the effort to additional accelerate the rate of progress while also not directly bringing in completion dates and shortening the schedule the place potential Motivate Project Team via incentives: Also, authorization may be obtained from Senior Management on the potential of incentivizing the staff with spot bonuses if finances may be allotted accordingly, to be able to maintain certain tight deadlines. This helps the group focus and work together to attain the frequent goal. Manage Overtime Pay and “Burnout”: On one other observe, on the subject of hours spent on the project by the project group, a course of could be reviewed with the team and proposals can be made to Senior Management weekly on whether overtime hours for employees who will be working their full 40 hours for the week may be approved or not. This won’t only hold a handle on prices because of overtime-pay, this may even forestall a sure element of “burnout” throughout the staff the place the staff would feel overworked.

Quality Assurance Metrics: Quality may be very relative and subjective. In order to take out the subjectivity from high quality measurement, the group can be asked to work collectively and provide you with tangible metrics to measure the standard of all the technical deliverables which are labored on. This will serve in obtaining an unbiased and tangible view of the progress made on any of the technical deliverables and measure readiness of the answer that is being worked on. With all the above listed recommendations in place this may not only pave the way for the profitable completion of the Telecommuting Expansion Project but set a really daring precedent within Xemba Translations as to what to do and what not to do in a project. The profitable completion of the Telecommuting Expansion Project would set a powerful basis for Xemba Translations to handle the extra enterprise that is forecasted starting in Q3.